Project Details


Client: St. Paul Port Authority
Location: St. Paul, MN
Services:  Demolition, Earthwork

Bolander began work in August of 2023 on one of Saint Paul’s largest site developments on the east side of the city. Located on the previous Hillcrest Golf Course, this civil development spans across the 112-acre site. Bolander’s scope of work at the site included the demolition of the existing golf course structures, site removals, soil remediation, soil corrections, and mass grading. This project is still ongoing, but crews are slated to be completed with our work during the 2024 construction season.

Project Highlights:

  • Excavation and Export of over 105,000 Tons of Mercury contaminated soil from the site
  • Excavation and Export of over 330,000 CYLV from the site to achieve site grades
  • Design-Build RSS Walls proposed by Bolander will be starting this summer. Integration of the RSS Walls saved money as well as reduced lead time of the originally designed concrete walls.

 

https://sppa.com/theheights